Tutorial

From TaskArtist Wiki

Jump to: navigation, search

The Tutorial Project

The Tutorial Project is an example project that helps you getting started with TaskArtist or taskjuggler respectively. You can find it inside the downloaded TaskArtist disk image or below. In order to use the Tutorial Project, you have to copy it to your hard disk or another writeable storage since TaskArtist will try to create reports at the location the project file resides. If this directory is not writeable, the creation of reports will fail.

To create reports using the Tuturial Project simply open it with TaskArtist and click the schedule button (or press the Command-Enter keys together). TaskArtist will then create reports for you. You can view them inside of TaskArtist or open them in an external viewer (your WebBrowser for example).

Please note: This file requires the latest version of TaskArtist to work since it uses recent features of the included taskjuggler subsystem.

The Tutorial File

/*
 * This file contains an example project. It is part of the
 * TaskJuggler project management tool. It uses a made up software
 * development project to demonstrate some of the basic features of
 * TaskJuggler. Please see the TaskJuggler manual for a more detailed
 * description of the various syntax elements.
 */
project acso "Accounting Software"  2002-01-16 +4m {
  # Set the default time zone for the project. If not specified, UTC
  # is used.
  timezone "Europe/Paris"
  # Hide the clock time. Only show the date.
  timeformat "%Y-%m-%d"
  # Use US format for numbers
  numberformat "-" "" "," "." 1
  # Use US financial format for currency values. Don't show cents.
  currencyformat "(" ")" "," "." 0
  # Pick a day during the project that will be reported as 'today' in
  # the project reports. If not specified, the current day will be
  # used, but this will likely be outside of the project range, so it
  # can't be seen in the reports.
  now 2002-03-05-13:00
  # The currency for all money values is the Euro.
  currency "USD"

  # We want to compare the baseline scenario to one with a slightly
  # delayed start.
  scenario plan "Plan" {
    scenario delayed "Delayed"
  }
  extend resource {
    text Phone "Phone"
  }
}

# This is not a real copyright for this file. It's just used as an example.
copyright "© 2002 Crappy Software, Inc."

# The daily default rate of all resources. This can be overridden for each
# resource. We specify this, so that we can do a good calculation of
# the costs of the project.
rate 390.0

# Register Good Friday as a global holiday for all resources.
vacation "Good Friday" 2002-03-29
flags team

# This is one way to form teams
macro allocate_developers [
  allocate dev1
  allocate dev2
  allocate dev3
]

# In order to do a simple profit and loss analysis of the project we
# specify accounts. One for the development costs, one for the
# documentation costs, and one account to credit the customer payments
# to.
account cost "Project Cost" {
  account dev "Development"
  account doc "Documentation"
}
account rev "Payments"
# The Profit&Loss analysis should be rev - cost accounts.
balance cost rev

resource boss "Paul Henry Bullock" {
  email "phb@crappysoftware.com"
  Phone "x100"
  rate 480
}
resource dev "Developers" {
  managers boss
  resource dev1 "Paul Smith" {
    email "paul@crappysoftware.com"
    Phone "x362"
    rate 350.0
  }
  resource dev2 "Sébastien Bono" {
    email "SBono@crappysoftware.com"
    Phone "x234"
  }
  resource dev3 "Klaus Müller" {
    email "Klaus.Mueller@crappysoftware.com"
    Phone "x490"
    vacation 2002-02-01 - 2002-02-05
  }
  flags team
}
resource misc "The Others" {
  managers boss
  resource test "Peter Murphy" {
    email "murphy@crappysoftware.com"
    Phone "x666"
    limits { dailymax 6.4h }
    rate 310.0
  }
  resource doc "Dim Sung" {
    email "sung@crappysoftware.com"
    Phone "x482"
    rate 300.0
    vacation 2002-03-11 - 2002-03-16
  }

  flags team
}

# Now we specify the work packages. The whole project is described as
# a task that contains subtasks. These subtasks are then broken down
# into smaller tasks and so on. The innermost tasks describe the real
# work and have resources allocated to them. Many attributes of tasks
# are inherited from the enclosing task. This saves you a lot of typing.
task AcSo "Accounting Software" {

  # All work-related costs will be booked to this account unless the
  # subtasks specify something different.
  chargeset dev
  # For the duration of the project we have running cost that are not
  # included in the labor cost.
  charge 170 perday
  responsible boss

  task spec "Specification" {
    # The effort to finish this task is 20 man-days.
    effort 20d
    # Now we use the macro declared above to allocate the resources
    # for this task. Because they can work in parallel, they may finish this
    # task earlier than in 20 working-days.
    ${allocate_developers}
    # Each task without subtasks must have a start or an end
    # criterion and a duration. For this task we use a reference to a
    # milestone defined further below as the start criterion. So this task
    # can not start before the specified milestone has been reached.
    # References to other tasks may be relative. Each exclamation mark (!)
    # means 'in the scope of the enclosing task'. To descent into a task, the
    # fullstop (.) together with the id of the tasks have to be specified.
    depends !deliveries.start
  }

  task software "Software Development" {

    # The software is the most critical task of the project. So we set
    # the priority of this task (and all its subtasks) to 1000, the top
    # priority. The higher the priority, the more likely the task will
    # get the requested resources.
    priority 1000

    # All subtasks depend on the specification task.
    depends !spec

    responsible dev1
    task database "Database coupling" {
      effort 20d
      allocate dev1, dev2
      journalentry 2002-02-03 "Problems with the SQL Libary" {
        author dev1
        alert yellow
        summary -8<-
          We ran into some compatibility problems with the SQL
          Library.
        ->8-
        details -8<-
          We have already contacted the vendor and are now waiting for
          their advise.
        ->8-
      }
    }

    task gui "Graphical User Interface" {
      effort 35d
      # This task has taken 5 man-days more than originally planned.
      # We record this as well, so that we can generate reports that
      # compare the delayed schedule of the project to the original plan.
      delayed:effort 40d
      depends !database, !backend
      allocate dev2, dev3
    }

    task backend "Back-End Functions" {
      effort 30d
      # This task is behind schedule, because it should have been
      # finished already. To document this, we specify that the task
      # is 95% completed. If nothing is specified, TaskJuggler assumes
      # that the task is on schedule and computes the completion rate
      # according to the current day and the plan data.
      complete 95
      depends !database
      allocate dev1, dev2
    }
  }

  task test "Software testing" {

    task alpha "Alpha Test" {
      # Efforts can not only be specified as man-days, but also as
      # man-weeks, man-hours, etc. By default, TaskJuggler assumes
      # that a man-week is 5 man-days or 40 man-hours. These values
      # can be changed, of course.
      effort 1w
      # This task depends on a task in the scope of the enclosing
      # task's enclosing task. So we need two exclamation marks (!!)
      # to get there.
      depends !!software
      allocate test, dev2
      note "Hopefully most bugs will be found and fixed here."
      journalentry 2002-03-01 "Contract with Peter not yet signed" {
        author boss
        alert red
        summary -8<-
          The paperwork is stuck with HR and I can't hunt it down.
        ->8-
        details -8<-
          If we don't get the contract closed within the next week,
          the start of the testing is at risk.
        ->8-
      }
    }

    task beta "Beta Test" {
      effort 4w
      depends !alpha
      allocate test, dev1
    }
  }

  task manual "Manual" {
    effort 10w
    depends !deliveries.start
    allocate doc, dev3
    purge chargeset
    chargeset doc
    journalentry 2002-02-28 "User manual completed" {
      author boss
      summary "The doc writers did a really great job to finish on time."
    }
  }

  task deliveries "Milestones" {

    # Some milestones have customer payments associated with them. We
    # credit these payments to the 'rev' account.
    purge chargeset
    chargeset rev

    task start "Project start" {
      # A task that has no duration is a milestone. It only needs a
      # start or end criterion. All other tasks depend on this task.
      # Here we use the built-in macro ${projectstart} to align the
      # start of the task with the above specified project time frame.
      start ${projectstart}
      # For some reason the actual start of the project got delayed.
      # We record this, so that we can compare the planned run to the
      # delayed run of the project.
      delayed:start 2002-01-20
      # At the beginning of this task we receive a payment from the
      # customer. This is credited to the account associated with this
      # task when the task starts.
      charge 21000.0 onstart
    }

    task prev "Technology Preview" {
      depends !!software.backend
      startcredit 31000.0
      note "All '''major''' features should be usable."
    }

    task beta "Beta version" {
      depends !!test.alpha
      charge 13000.0 onstart
      note "Fully functional, may contain bugs."
    }

    task done "Ship Product to Customer" {
      # The next line can be uncommented to trigger a warning about
      # the project being late. For all tasks, limits for the start and
      # end values can be specified. Those limits are checked after the
      # project has been scheduled. For all violated limits a warning
      # is issued.
      # maxend 2002-04-17
      depends !!test.beta, !!manual
      charge 33000.0 onstart
      note "All priority 1 and 2 bugs must be fixed."
    }
  }
}

# Now the project has been specified completely. Stopping here would
# result in a valid TaskJuggler file that could be processed and
# scheduled. But no reports would be generated to visualize the
# results.

navigator navbar {
  hidereport 0
}

macro TaskTip [
  tooltip istask() -8<-
    '''Start: ''' <-query attribute='start'->
    '''End: ''' <-query attribute='end'->
    ----
    '''Resources:'''

    <-query attribute='resources'->
    ----
    '''Precursors: '''

    <-query attribute='precursors'->
    ----
    '''Followers: '''

    <-query attribute='followers'->
    ->8-
]

textreport frame "" {
  header -8<-
    == Accounting Software Project ==
    ----
    <[navigator id="navbar"]>
    ----
  ->8-
  footer "----"
  textreport index "Overview" {
    formats html
    center '<[report id="overview"]>'
  }

  textreport "Status" {
    formats html
    center -8<-
      <[report id="status.dashboard"]>
      ----
      <[report id="status.completed"]>
      ----
      <[report id="status.ongoing"]>
      ----
      <[report id="status.future"]>
    ->8-
  }

  textreport development "Development" {
    formats html
    center '<[report id="development"]>'
  }

  textreport "Deliveries" {
    formats html
    center '<[report id="deliveries"]>'
  }

  textreport "ContactList" {
    formats html
    title "Contact List"
    center '<[report id="contactList"]>'
  }
  textreport "ResourceGraph" {
    formats html
    title "Resource Graph"
    center '<[report id="resourceGraph"]>'
  }
}

# A traditional Gantt chart with a project overview.
taskreport overview "" {
  header -8<-
    === Project Overview ===

    The project is structured into 3 phases.

    # Specification
    # <-reportlink id='frame.development'->
    # Testing

    === Original Project Plan ===
  ->8-
  columns hierarchindex,
          name, start, end, effort, duration, cost,
          revenue, chart { ${TaskTip} }
  # For this report we like to have the abbreviated weekday in front
  # of the date. %a is the tag for this.
  timeformat "%a %Y-%m-%d"
  loadunit days
  hideresource 1
  balance cost rev
  caption 'All effort values are in man days.'

  footer -8<-
    === Staffing ===

    All project phases are properly staffed. See [[ResourceGraph]] for
    detailed resource allocations.

    === Current Status ===

    The project started off with a delay of 4 days. This slightly affected
    the original schedule. See [[Deliveries]] for the impact on the
    delivery dates.
  ->8-
}

# Macro to set the background color of a cell according to the alert
# level of the task.
macro AlertColor [
  cellcolor plan.alert = 0 "#00D000" # green
  cellcolor plan.alert = 1 "#D0D000" # yellow
  cellcolor plan.alert = 2 "#D00000" # red
]

taskreport status "" {
  columns wbs { width 50 }, name { width 150 },
          start { width 100 }, end { width 100 },
          effort { width 100 },
          alert { tooltip plan.journal
                          != '' "<-query attribute='journal'->" width 150 },
          status { width 150 }
  scenarios delayed

  taskreport dashboard "" {
    headline "Project Dashboard (<-query attribute='now'->)"
    columns name { title "Task" ${AlertColor} width 200},
            resources { width 200 ${AlertColor}
                        listtype bullets listmode 2
                        start ${projectstart} end ${projectend} },
            alerttrend { title "Trend" ${AlertColor} width 50 },
            journalmessages { width 350 ${AlertColor} }
    hidetask ~hasalert(0)
    sorttasks alert.down, delayed.end.up
    period %{${now} - 1w} +1w
  }
  taskreport completed "" {
    headline "Already completed tasks"
    hidetask ~(delayed.end <= ${now})
  }
  taskreport ongoing "" {
    headline "Ongoing tasks"
    hidetask ~((delayed.start <= ${now}) & (delayed.end > ${now}))
  }
  taskreport future "" {
    headline "Future tasks"
    hidetask ~(delayed.start > ${now})
  }
}

# A list of tasks showing the resources assigned to each task.
taskreport development "" {
  scenarios delayed
  headline "Development - Resource Allocation Report"
  columns hierarchindex, name, start, end, effort { title "Work" },
          duration, chart { ${TaskTip} scale day width 500 }
  timeformat "%Y-%m-%d"
  hideresource ~(isleaf() & isleaf_())
  sortresources name.up
}

# A list of all tasks with the percentage completed for each task
taskreport deliveries "" {
  headline "Project Deliverables"
  columns hierarchindex, name, start, end, note { width 150 }, complete,
          chart { ${TaskTip} }
  taskroot AcSo.deliveries
  hideresource 1
  scenarios plan, delayed
}
# A list of all employees with their contact details.
resourcereport contactList "" {
  scenarios delayed
  headline "Contact list and duty plan"
  columns name,
          email { celltext 1 "[mailto:<-email-> <-email->]" },
          Phone,
          managers { title "Manager" },
          chart { scale day }
  hideresource ~isleaf()
  sortresources name.up
  hidetask 1
}

# A graph showing resource allocation. It identifies whether each
# resource is under- or over-allocated for.
resourcereport resourceGraph "" {
  scenarios delayed
  headline "Resource Allocation Graph"
  columns no, name, effort, rate, weekly { ${TaskTip} }
  loadunit shortauto
  # We only like to show leaf tasks for leaf resources.
  hidetask ~(isleaf() & isleaf_())
  sorttasks plan.start.up
}